Home builders typically understand the concept of critical path scheduling. It’s easy to understand that certain items must be done before the next activity can start (e.g. mechanical rough-ins must be complete before the inspection can happen).
There’s another scheduling concept that is often lesser-understood and often confused with critical path scheduling, and that’s a concept known as push type scheduling.
Push type scheduling works hand-in-hand with critical path scheduling, but they are not the same thing. I hope to clear up any confusion with this post.
Specifically, there are two different push type schedule designations:
· Push
· No-Push
When a software system is set to push scheduling, any schedule activity that is scheduled to complete today - but NOT marked as complete today – will automatically push the completion date until the next scheduled business day. The start date for any activity that is scheduled to occur after this activity is complete (assuming this activity is a predecessor in that critical path) will also push to the appropriate next start date – essentially continuing to push the schedule until the original schedule activity is marked complete.
Compare that to no-push scheduling. With that schedule designation, any schedule activity that is scheduled to complete today – but NOT marked as complete today – will keep its completion date today and NOT push the completion date. The start date for any activity that is scheduled to occur after this activity is complete (assuming this activity is a predecessor in that critical path) will also remain as scheduled.
Both push designations have their own advantages and disadvantages, and you can make an argument for why you might want to use one over the other.
Advantages/disadvantages of push scheduling
The big advantage to the push schedule designation is that it minimizes “dry runs” (and the associated backcharges from the trade contractors) – since the next trade contractor’s start date keeps pushing UNTIL the previous critical path schedule item is marked complete.
So, superintendents who don’t actively manage their schedules every day may find that their build times are longer than they want them to be. If they don’t mark an item complete today (that really is complete), the next trade contractor in line will think their scheduled activity is not ready (since the schedule pushed their start date to the next scheduled business day).
This means that superintendents are then spending a lot more time manually managing the trades’ schedules, instead of using the software efficiently to handle those schedules.
The owners of home building companies who like this designation believe it ensures their superintendents are managing their job schedules more efficiently every day. And – for those who structure compensation plans based on schedule length – there is an extra incentive for those superintendents to ensure their schedule pushes as little as possible.
The big advantage to the no-push schedule designation is that many superintendents find it easier to manage their schedules based on their time schedules, and they feel they have more control over when their trades will show up.
After all, they know that no two house schedules are exactly the same. Delays due to weather, inspections, labor shortages, material shortages, etc. will affect the schedule, and schedule overlap can (and will) happen. This allows the critical path to be managed manually when some scheduled activities can not be marked complete but other activities still need to start.
Be warned, though. If an activity scheduled to complete today truly is NOT complete today, and that activity does need to be complete before the next critical-path scheduled activity can start, superintendents must ensure that they notify the next trade contractor that the job is not ready. If they don’t, the trade contractor will likely show up and not be able to work, and that costs them (and, ultimately, the home builder) money.
The owners of home building companies who like this designation believe their superintendents take more ownership of the schedule and have less reason to “fudge” the system. And those owners who structure compensation plans based on schedule length believe they can still hold the superintendents accountable to their targeted completion dates.
The short answer: whichever works best for you and your team. Both approaches still lend themselves best to those superintendents who manage their schedules every day.
Rather than relying on the schedule to push or not, the most effective superintendents are taught to use schedule exceptions to manage their schedules. By doing so, the superintendents are providing key data to management on what is really happening on the job.
That data helps management make decisions on trade contractors, material sourcing, plan reviews, and/or superintendent effectiveness.